TOKYO, March 27 (Reuters) - Kyushu Electric Power
9508.T has shut the No.4 reactor at its Genkai nuclear power
station in southern Japan for scheduled maintenance, a company
spokesperson said on Wednesday.
The 1,180-megawatt (MW) reactor was suspended early on
Wednesday and is scheduled to restart in June, the spokesperson
added.
While the No.4 reactor was in the process of reducing power,
an alarm sounded late on Tuesday, indicating uneven power levels
within the reactor, the company said in a statement.
But the alarm ceased after eight minutes, without causing
any radiation impact on the environment, the company added.
Meanwhile, Kansai Electric Power 9503.T has also shut the
1,180-MW No.3 reactor at its Ohi nuclear power station for
scheduled maintenance on Feb. 10, with a plan to reboot the
reactor in early April, a company spokesperson said.
With the shutdowns, Japan now has nine operating reactors
with a total capacity of 8,378 MW.
Many companies are still going through a relicensing
process to comply with stricter safety standards imposed after
the 2011 Fukushima disaster. The companies had 54 operational
reactors before the disaster.
The table below shows the status of Japan's nuclear power
plants.
The regional utilities are: Chubu Electric Power 9502.T ,
Chugoku Electric Power 9504.T , Hokkaido Electric Power
9509.T , Hokuriku Electric Power 9505.T , Kansai Electric
Power 9503.T , Kyushu Electric Power 9508.T , Shikoku Electric
Power 9507.T , Tohoku Electric Power 9506.T and Tokyo
Electric Power (Tepco) 9501.T .
They are referred to in the table by their regional names.
Company Plant Unit MW Status
Hokkaido Tomari 1 579 Shutdown 22/4/11
Hokkaido Tomari 2 579 Shutdown 26/8/11
Hokkaido Tomah 3 912 Shutdown 5/5/12
Tohoku Onagawa 2 825 Shutdown 6/11/10
Tohoku Onagawa 3 825 Shutdown 11/3/11
Tohoku Higashidori 1 1,100 Shutdown 6/2/11
Tepco Kashiwazaki-Kariwa 1 1,100 Shutdown 6/8/11
Tepco Kashiwazaki-Kariwa 2 1,100 Shutdown 16/7/07
Tepco Kashiwazaki-Kariwa 3 1,100 Shutdown 16/7/07
Tepco Kashiwazaki-Kariwa 4 1,100 Shutdown 16/7/07
Tepco Kashiwazaki-Kariwa 5 1,100 Shutdown 25/1/12
Tepco Kashiwazaki-Kariwa 6 1,356 Shutdown 26/3/12
Tepco Kashiwazaki-Kariwa 7 1,356 Shutdown 23/8/11
Chubu Hamaoka 3 1,100 Shutdown 29/11/10
Chubu Hamaoka 4 1,137 Shutdown 13/5/11
Chubu Hamaoka 5 1,380 Shutdown 14/5/11
Hokuriku Shika 1 540 Shutdown 1/3/11
Hokuriku Shika 2 1,206 Shutdown 11/3/11
Kansai Mihama 3 826 Online 18/1/24
Kansai Takahama 1 826 Online 28/7/23
Kansai Takahama 2 826 Online 15/9/23
Kansai Takahama 3 870 Online 22/12/23
Kansai Takahama 4 870 Shutdown 16/12/23
Kansai Ohi 3 1,180
Shutdown 10/2/24
Kansai Ohi 4 1,180 Online 25/10/23
Chugoku Shimane 2 820 Shutdown 27/1/12
Shikoku Ikata 3 890 Online 24/5/23
Kyushu Genkai 3 1,180 Online 10/12/22
Kyushu Genkai 4 1,180
Shutdown 27/3/24
Kyushu Sendai 1 890 Online 21/4/23
Kyushu Sendai 2 890 Online 16/7/23
Japco Tokai Daini 1 1,100 Shutdown 11/3/11
Japco Tsuruga 2 1,160 Shutdown 7/5/11
Total 33,083