TOKYO, Jan 18 (Reuters) - Kansai Electric Power 9503.T
has restarted the No. 3 reactor at its Mihama nuclear power
station in western Japan after scheduled maintenance, a company
spokesperson said on Thursday.
The 826-megawatt (MW) reactor was rebooted mid-Thursday.
The utility company has also restarted the 870-MW No.3
reactor at its Takahama nuclear power station after scheduled
maintenance on Dec. 22, 2023, while shutting the 870-MW No.4
reactor at Takahama for planned maintenance on Dec. 16, the
spokesperson said.
With the restarts and shutdown, Japan has 11 operating
reactors with a total capacity of 10,738 MW.
Many companies are still going through a relicensing process
to comply with stricter safety standards imposed after the 2011
Fukushima disaster. The companies had 54 operational reactors
before the disaster.
The table below shows the status of Japan's nuclear power
plants.
The regional utilities are: Chubu Electric Power 9502.T ,
Chugoku Electric Power 9504.T , Hokkaido Electric Power
9509.T , Hokuriku Electric Power 9505.T , Kansai Electric
Power 9503.T , Kyushu Electric Power 9508.T , Shikoku Electric
Power 9507.T , Tohoku Electric Power 9506.T and Tokyo
Electric Power (Tepco) 9501.T .
They are referred to in the table by their regional names.
Company Plant Unit MW Status
Hokkaido Tomari 1 579 Shutdown 22/4/11
Hokkaido Tomari 2 579 Shutdown 26/8/11
Hokkaido Tomah 3 912 Shutdown 5/5/12
Tohoku Onagawa 2 825 Shutdown 6/11/10
Tohoku Onagawa 3 825 Shutdown 11/3/11
Tohoku Higashidori 1 1,100 Shutdown 6/2/11
Tepco Kashiwazaki-Kariwa 1 1,100 Shutdown 6/8/11
Tepco Kashiwazaki-Kariwa 2 1,100 Shutdown 16/7/07
Tepco Kashiwazaki-Kariwa 3 1,100 Shutdown 16/7/07
Tepco Kashiwazaki-Kariwa 4 1,100 Shutdown 16/7/07
Tepco Kashiwazaki-Kariwa 5 1,100 Shutdown 25/1/12
Tepco Kashiwazaki-Kariwa 6 1,356 Shutdown 26/3/12
Tepco Kashiwazaki-Kariwa 7 1,356 Shutdown 23/8/11
Chubu Hamaoka 3 1,100 Shutdown 29/11/10
Chubu Hamaoka 4 1,137 Shutdown 13/5/11
Chubu Hamaoka 5 1,380 Shutdown 14/5/11
Hokuriku Shika 1 540 Shutdown 1/3/11
Hokuriku Shika 2 1,206 Shutdown 11/3/11
Kansai Mihama 3 826 Online
18/1/24
Kansai Takahama 1 826 Online 28/7/23
Kansai Takahama 2 826 Online 15/9/23
Kansai Takahama 3 870 Online
22/12/23
Kansai Takahama 4 870
Shutdown 16/12/23
Kansai Ohi 3 1,180 Online 16/12/22
Kansai Ohi 4 1,180 Online 25/10/23
Chugoku Shimane 2 820 Shutdown 27/1/12
Shikoku Ikata 3 890 Online 24/5/23
Kyushu Genkai 3 1,180 Online 10/12/22
Kyushu Genkai 4 1,180 Online 7/2/23
Kyushu Sendai 1 890 Online 21/4/23
Kyushu Sendai 2 890 Online 16/7/23
Japco Tokai Daini 1 1,100 Shutdown 11/3/11
Japco Tsuruga 2 1,160 Shutdown 7/5/11
Total 33,083
(Reporting by Yuka Obayashi; Editing by Tasim Zahid)
((Yuka.Obayashi@thomsonreuters.com; +813-4520-1265;))