April 24 (Reuters) - Hudson Resources Inc HUD.V :
* HUDSON RESOURCES PROVIDES UPDATE ON THE PROCESS PLANT RAMP
UP AT
THE WHITE MOUNTAIN ANORTHOSITE MINE
* HUDSON RESOURCES INC - WHITE MOUNTAIN PROCESS PLANT RAMP
UP HAS
ACHIEVED 50% CAPACITY AND PRODUCTION CONTINUES TO INCREASE
* HUDSON RESOURCES INC - ENCOUNTERED SOME PRODUCTION ISSUES
ASSOCIATED WITH EXTREMELY COLD TEMPERATURES IN FEBRUARY AND
MARCH
* HUDSON RESOURCES - WILL INSTALL A HEATER SYSTEM THIS
SUMMER TO
MANAGE PRODUCTION ISSUES ASSOCIATED WITH EXTREMELY COLD
TEMPERATURES FOR NEXT WINTER
* HUDSON RESOURCES INC - COLD TEMPERATURE IS CURRENTLY NOT
AN
ISSUE FOR PLANT OPERATIONS.
* HUDSON RESOURCES INC - AT CURRENT OPERATING PARAMETERS, WE
ARE
ON TRACK TO MEET OUR SHIPMENT TARGETS FOR THIS YEAR
* HUDSON RESOURCES INC - ANTICIPATE WILL HAVE OUR FIRST
SHIPMENT
OF GREENSPAR READY FOR LOADING BY END OF JUNE
Source text for Eikon: ID:nGNX964Qpf
Further company coverage: HUD.V
((Reuters.Briefs@thomsonreuters.com;))